Thank you Caetano.
Is this replenishment lead time setup on MRP3 view? or The PDT+GR processing time maintained in the MRP2 view ?
I do not want to change my PDT+GR processing time which is now set to: 15 days.
I want reorder point planning to consider sales order only within next 30 days period and not after that. So if I adjust my PDT+GR on MRP2 view, then it will also affect the 15 days schedule for delivery when purchase orders were created, which I want to avoid.
Please let me know your thoughts
thank you